The fan on #12 is almost complete. Weather has been a continuous problem over the past couple weeks to complete this project. Last week contractors were able to dig the trenches and install the conduit from the power source along the neighborhood street to the green site. Currently we are waiting on an inspection to be able to fill in the trenches and install the wiring. After installing the wiring, a final inspection will occur and NES will install the meter globe and we will be up an running. We are hopeful to be operating the fan early next week.